ANSI/ISA-62381-2011 (IEC 62381 Modified)

Automation Systems in the Process Industry - Factory Acceptance Test (FAT), Site Acceptance Test (SAT)

ISA
Engineering
Standard

3

Checklist Items

3

FAQs

3

Glossary Terms

Dec 11, 2025

Last Updated

Classification

Topics & metadata

FolderIndustrial Automation
Sub-domainAutomation and Control Systems
TypeStandard Specification
Year2011
StatusActive
LevelExpert
Summary

This standard specifies requirements for Factory Acceptance Tests (FAT), Site Acceptance Tests (SAT), and Site Integration Tests (SIT) for automation systems used in the process industry.

ANSI/ISA-62381-2011 (IEC 62381 Modified): Automation Systems in the Process Industry - Factory Acceptance Test (FAT), Site Acceptance Test (SAT), and Site Integration Test (SIT)

Ensuring the seamless and reliable operation of automation systems is paramount in the complex world of process industries. ANSI/ISA-62381-2011 provides the essential framework for verifying these critical systems before they are deployed, mitigating risks and ensuring operational readiness. This authoritative standard offers a proven methodology for executing Factory Acceptance Tests (FAT), Site Acceptance Tests (SAT), and Site Integration Tests (SIT), making it an indispensable resource for engineers and project managers.

What is ANSI/ISA-62381-2011 (IEC 62381 Modified)?

This comprehensive standard, a modified adoption of IEC 62381, establishes a unified approach to testing automation systems within process industries. Its primary purpose is to define the procedures and criteria for conducting FAT, SAT, and SIT, ensuring that control systems function as intended and integrate correctly with the overall plant infrastructure before and during commissioning.

Scope & Purpose

ANSI/ISA-62381-2011 governs the systematic testing of automation systems, encompassing hardware, software, and their integration. It details the planning, execution, and documentation of tests performed at the vendor's facility (FAT), at the end-user's site (SAT), and when integrating different components of the automation system on-site (SIT). The standard focuses on verifying functionality, performance, and safety aspects of the automation system in its intended operational environment. It does not cover the detailed design of individual components, but rather the verification of their integrated performance.

Who Must Comply?

  • Primary audience: Automation Engineers, Control Systems Engineers, Instrumentation Engineers, Project Managers, Commissioning Engineers, and System Integrators.
  • Industries affected: Chemical, Oil and Gas, Pharmaceuticals, Food and Beverage, Water and Wastewater, and other process manufacturing sectors.
  • Compliance nature: Recommended, but often becomes a de facto requirement for quality assurance and contractual obligations.
  • Enforcement: Typically enforced by project owners, engineering firms, and regulatory bodies through contract specifications and audit processes.

Key Requirements Overview

  • The standard requires the development of detailed test plans for FAT, SAT, and SIT, clearly outlining objectives, procedures, and acceptance criteria.
  • Professionals must ensure that test environments accurately simulate operational conditions to validate system performance effectively.
  • Key provisions include the verification of control logic, alarm management, interlocks, communication protocols, and human-machine interface (HMI) functionality.
  • Documentation is a critical component, mandating thorough recording of test results, deviations, and resolutions to ensure traceability and facilitate future maintenance.
  • The standard emphasizes a phased approach to testing, progressively validating system components and their integration to ensure overall system integrity.

Related Standards & References

This standard frequently works in conjunction with other ISA documents, such as those related to instrumentation specifications (e.g., ANSI/ISA standards for specific instruments) and safety systems (e.g., ANSI/ISA-84, now IEC 61511, for functional safety). It also aligns with broader project management

Copyright & official sources

This page provides educational summaries and compliance aids. For the official, legally binding standard text, please purchase the current edition from the original publisher. Acquiring original publications supports continued standards development and ensures you have the complete, authoritative document.